Intensive monitoring of the critical point 01 Bala within the “Monitoring the environmental impact of the works regarding the improvement of the navigation conditions on the Danube river between Calarasi and Braila, km 375-175” project

 This page will be permanently updated

OBJECTIVE:

1) Comparative analysis of the results of numerical modelling of the Danube flow at different levels (for initial phase and the 3rd phase of execution of bottom sill on Bala branch) and the results obtained in the field by daily measurements in different sections of control.
2) Determining the speed of sturgeon above the bottom sill on Bala branch. news

PURPOSE: In order to prevent possible misunderstandings of the hydrological phenomena and sturgeons’ migration, a new monitoring and alarming system has been implemented.

sistem monitorizare eng
Figure 1 – Monitoring system to check the results obtained by 3D numerical simulations

sistem monitorizare sturioni Bala 3 en
Figure 2 – Intensive monitoring system in the area of interest to determine sturgeons’ movement velocity (patent proposal)
pf 011 pf 021
Image of the bottom sill zone as a result of bathymetric measurements Image of the bottom sill zone as a result of bathymetric measurements
pf 031
Image of the bottom sill zone as a result of bathymetric measurements
img statie fixa s1 img statie fixa s2
Fixed station for sturgeon monitoring S1 installed on 13th of July 2013 Fixed station for sturgeon monitoring S2 installed on 16th of July 2013
img statie fixa s1 2 img statie fixa s2 2
Fixed station for sturgeon monitoring S1, repositioned due the decrease of water level and destroyed by a barge on 24th of August 2013 Fixed station for sturgeon monitoring S2, repositioned due the decrease of water level
img baliza S1 img baliza S2
Floating station for sturgeon monitoring S1 installed on 21st of July 2013. During August 2013 this monitoring floating station has been destroyed Floating station for sturgeon monitoring S2 installed on 21st of July 2013. During August 2013 this monitoring floating station has been disabled to avoid losing or destroying
img montare statie 1  img montare statie 2
Installing the fixed station for sturgeon monitoring S1 on 13th of July 2013 Installing the fixed station for sturgeon monitoring S1 on 13th of July 2013
img instalare baliza s1 img instalare baliza s2
Fixing the receiver to the floating station for sturgeon monitoring S1 Fixing the receiver to the floating station for sturgeon monitoring S2
btn control en


Therefore, beside the monitoring activity of the environmental biotic and abiotic parameters (according to contract no. 53/2011) an additional investigation, carried out in emergency regime of the following parameters has been made:

A) Monitored parameters according to the next table:

Continuous measurements Quasi-continuous measurements
-water turbidity
-water salinity
-water temperature
-water level
-detection of sturgeons migration
-velocity of water flow
-discharge
-bathymetry
-water surface level
-x, y, z coordinates of monitoring devices

B) Determination of reception areas of the ultrasonic emitters placed within sturgeons’ body  (still implementing)
C) Determination of sturgeons’ movement velocity in the area of Bala bottom sill (this will be implemented after the obtaining of the scientific fishing authorization)*
D) Checking activity of the hydrological parameters before and after the accomplishment of the bottom sill- Phase III, Bala (in the first part of September)
E) Checking of the forecasts accomplished through the numerical simulation and comparative analysis (result of the 3D numerical model- in situ measurements (September)

The accomplishment steps to ensure the success of the intensive monitoring activity are:

Position of the control center, on Bala branch Control center

Members of the on-site monitoring teams
Members of the field control team Members of the measurements’ control team

Expert PhD Eng UNGUREANU Gheorghe
Expert Assist. Eng. BÂDILIŢĂ Alin
Biol. FRIM Alina - Biodiversity Resp.
S.R. PhD Eng Lucian LASLO
S.R. Eng. BÂDILIŢĂ Alin
S.R.A Eng. OLTEANU Marius
Geogr. MANOLIU Alexandru
S.R.A. Eng. CRISTEA Alexandru
S.R. PhD Eng. ZAHARIA Ionuţ
S.R.A. Eng. IVANOV Alexandru
S.R.A. Geogr. IOSIF Andrei
S.R.A. Eng. SÎRBU Vlad
Techn. topographer Gabriel CORNĂȚEANU
Techn. Traian PÂRVULESCU
Techn. BĂNICĂ Gabriel
Techn. CHINAN Adrian
Techn. MARIN Nicolae
Techn. POPA Marian
Techn. VISALON Marius

S.R. I Eng. DEÁK György Ph.D
S.R. III RAISCHI Marius
S.R.A. Eng. SILION Mădălin
S.R.  II Mathem. PETRESCU Alexandru
S.R.A. Geogr. URIŢESCU Bogdan
S.R.A. Eng. BĂLĂNESCU Cezar – Informatics Project Manager

flux informational 2 eng

Expected results:

  1. 3D Model audit and recalibration
  2. Assurance of a high confidence level of the future forecast results of the 3D numerical models for the entire geometry of Bala bottom sill
  3. Determination - with an assumed reliability - of sturgeons’ movement velocity in natural conditions, on Bala (especially at bottom sill)
  4. Highlighting sturgeons’ migration routes in the investigated area
  5. Maps containing sturgeons’ migration  routes in the investigated areas
  6. Decisional analysis on sturgeons’ migrating possibility according to the final geometry of bottom sill, Bala branch
  7. Preventive solutions proposals to eliminate/decrease any risk impact on the aquatic or terrestrial environment.

Obtained results:
The synthetic situation of the measurements carried out by the detached teams is presented below:

{jumi [images/monitorizare_intensiva/teams_table.php]}


 
The aerial image of the monitoring area is being presented as well as the sections on which the intensive monitoring is being carried out. You may click the names of the monitored sections to view the historic of the measurements as well as the results of 3D models for these sections.

Click pentru detalierea informațiilor Click pentru detalierea informațiilor Click pentru detalierea informațiilor Click pentru detalierea informațiilor Click pentru detalierea informațiilor Click pentru detalierea informațiilor Click pentru detalierea informațiilor

btn debite en

Ending deadline: 30 November 2013 – according to the field conditions and the hydrotechnical works this deadline can be extended to 3 months maximum.

Responsible for webpage content Eng. DEÁK György Ph.D
Biol. FRIM Alina - biodiversity resp.
Matem. PETRESCU Alexandru
CS III RAISCHI Marius
Geogr. MANOLIU Alexandru
   
Responsible for the functioning of the webpage Eng. BĂLĂNESCU Cezar - IT Project Manager